REC Ltd developed a strategy for the remediation
of the site involving removal of contaminated
soils and the treatment of contaminated
groundwater by means of a permeable reactive
wall. The design and performance criteria
for the permeable reactive wall was designed
by REC Ltd and Envirotreat, a specialist
contractor.
The design of the permeable reactive wall
was approved by the Environment Agency after
the development of a working plan. The performance
of the permeable reactive wall has been monitored
by REC Ltd for over six months with routine
chemical testing of the groundwater both
'upstream' and 'downstream' of the structure.
To date, TBT concentrations downstream of
the structure are negligable.
For further information on the Contaminated
Land services offered by REC, click
here. |